Requesting approval of a revised appropriation of $39,511,429 for the cost of rehabilitation and renovation of the East Somerville Community School.
body
Official Text
To the Honorable Board:
I respectfully request approval of a revised appropriation of $39,511,429 and authorization to borrow $39,511,429 for the cost of rehabilitation and renovation of the East Somerville Community School in order to repair severe damage incurred during a 2007 fire at the school.
The total project budget appropriation for the East Somerville Community School Project is as outlined below:
Insurance Proceeds $10,023,433
City of Somerville General Obligation Bond $ 8,000,000
MSBA Low Interest Loan $ 6,250,000
MSBA Maximum Facilities Grant $ 15,237,996
TOTAL PROJECT BUDGET $39,511,429
Respectfully,
Joseph A. Curtatone
Mayor
Condition
That the Administration provide a detailed explanation of how the additional $6,250,000 for the project will be used.
NOTE: The condition was met on Friday, July 20, 2012.